Supply Control Tower (demo)
As of ·
Supplier OTIF
On time in full by supplier, lines promised in the last 12 months. Worst first.
OTIF trend
Monthly OTIF % by promised month, with on-time % and in-full % shown separately.
Lead-time variance
Average actual lead time (order to first receipt) minus the supplier's quoted lead time, in days.
Open PO aging
Open value (ordered minus received, at PO price) by days past the promised date. Hover a bar for line counts.
Inventory days of supply
On hand ÷ average daily usage (last 180 days), by item. Red bars are below safety stock.
Stockout risk list
Items whose stock runs out before the next open PO is promised to arrive, or that have no inbound PO and less cover than the supplier's lead time.
| Risk | Item | Supplier | Days of supply | Runs out | Next inbound | Gap (days) | PO |
|---|
How these numbers are calculated
- OTIF: a non-cancelled PO line promised on or before the as-of date counts as on time in full when quantity received is at least quantity ordered and the last receipt date is on or before the promised date.
- Lead-time variance: first receipt date minus order date, minus the supplier's quoted lead time. Positive means slower than quoted.
- Open PO aging: open and partially received lines; open value = (ordered − received) × unit price; days late measured from the promised date.
- Days of supply: on-hand quantity ÷ average daily usage. Usage is approximated from receipts over the last 180 days.
- Stockout risk: High when the stockout date falls before the next open PO's promised date (or no PO is open and cover is shorter than the quoted lead time). Medium when cover is below safety-stock days. Otherwise Low.
The same logic ships as DAX measures in the Power BI build kit, so the real report matches this demo.